Structural Condition Assessment and Repairs ‐ Update - August 2023

August 9, 2023, HOA MEETING

  • All concrete repairs in the catacombs, as well as all parking structure ceiling repairs, except for a small area beneath the entry ramp, have been completed. Epoxy injection into the two small remaining cracks is scheduled for August 11.

  • The City of San Diego Building Department has completed their final inspection and, on August 3, signed off on the structural repairs.

  • During construction, our structural engineers, Degenkolb, completed site inspections on June 12, June 20, July 5, and July 26 and has provided site visit reports to Nautilus. Degenkolb has also reviewed all concrete‐repair subcontractor submittals associated with the work.

  • Degenkolb is currently preparing a “final” observation letter, as required by City. They are also preparing a similar document for the Bay Scene Owners Association stating that the identified structural issues have been repaired.

  • July 17th was the last day that Nautilus poured/patched concrete. Allowing 21 days for the concrete to cure, the shoring can now be removed.

Robert Citrano