• CONCRETE TESTING
∙ Degenkolb Engineers, our structural engineering consultant, has prepared a concrete testing program to sample areas where decades of infiltrating water have affected the catacomb floor/garage ceiling…
Read More• CONCRETE TESTING
∙ Degenkolb Engineers, our structural engineering consultant, has prepared a concrete testing program to sample areas where decades of infiltrating water have affected the catacomb floor/garage ceiling…
Read MoreYou will have noticed that the temporary shoring towers and columns have been installed in our parking structure. As discussed in previous updates and HOA meetings, this shoring is to ensure structural integrity while repairs are being made to the concrete slab that forms the garage ceiling…
Read MoreThe north pedestrian gate off of Gresham Street is closed and pending repair. Please do not use this gate until further notice.
Read MoreIf you have a bike, kayak, or stand-up paddle board being stored at Bay Scene, you will need to have your annual sticker displayed by August 1, 2022. If you are storing a boat, large or small, your renewal fee is due by August 1, 2022…
Read MoreWi-Fi service in the garage has been restored. Thank you for your patience.
Read MoreThe Wi-Fi service in the garage is currently out of service. We are attempting negotiations with the Internet Service Provider to get service restored, but this may take a while. We apologize for the inconvenience.
Read MorePlease be advised that the July 13th, 2022 Board of Directors meeting has been cancelled. The next meeting is scheduled for August 10, 2022, at 6:00PM.
Read MoreAfter a delay due to supply‐chain issues, the installation of temporary shoring in three areas of our parking structure is scheduled to begin this week. Shoring components will be…
Read More Temporary shoring of selected areas in our parking structure will commence in the next 2‐3 weeks. Supply‐chain issues have delayed delivery of shoring towers. We’ll send out another announcement when installation is firmly scheduled.
Degenkolb Engineers, our structural engineering…