Windows Replacement Project - Phase 2 Update May 2022

MAY 23, 2022, HOA MEETING

The draft proposal for Phase 2 services has been reviewed by Board and Windows Committee members. Our windows consultant, Whitmore Architects, is incorporating our comments into a final proposal for review by Bay Scene's legal counsel. We anticipate Phase 2 work will begin in early June.

  • The initial Phase 2 task, "Design Development Services," includes working with window manufacturers, fenestration expert, structural engineer, general contractor, and value engineering specialists, to select an optimal window system; then prepare design development drawings, findings, and a refined estimate of project cost.

  • Approximately two months will be needed to complete Phase 2, after which there will be one or two Town Hall meetings to present findings to our homeowners.

  • Following these presentations, a homeowner's vote will be conducted asking whether we should proceed with the windows replacement project.

Jimmy Gottlieb